Room Additions in Tarzana | Case Study | Oria Builders
| Project Type | Room Additions |
|---|---|
| Location | Tarzana, CA (Melody Acres) |
| Investment | $85,000 - $120,000 |
| Duration | 10 weeks |
| Completed | 2023-08-15 |
The Challenge
The homeowners in Melody Acres, Tarzana, faced a common yet complex challenge. As their family expanded, so did their need for more space. However, the existing structure, a charming mid-century design, left little room for growth without careful planning. They wanted to preserve the architectural integrity that characterized their neighborhood while adding functional living space. Tarzana, known for its lush landscapes and variety of home styles, demands thoughtful integration of new structures. The homeowners sought a partner who understood the local building codes and could navigate the intricate permit process, ensuring their addition would comply with Tarzana’s aesthetic and regulatory standards.
Our Approach
Oria Builders began the project by holding detailed design meetings with the homeowners. We focused on understanding their lifestyle needs and aesthetic preferences, translating these into a practical design that complemented the existing home and neighborhood. Material selection was a collaborative process, involving the homeowners in choosing materials that were both durable and in harmony with the mid-century style. Navigating the permit process in Tarzana can be complex, but our team, well-versed in local regulations, handled the paperwork efficiently, securing the necessary approvals without delay. This ensured a smooth start to the construction phase, aligning with the project timeline.
Build Process
The construction phase kicked off with the careful demolition of a section of the existing home to make way for the new addition. Our skilled craftsmen took precise measurements to ensure that every new element integrated seamlessly with the old structure. We focused on high-quality craftsmanship, using advanced framing techniques to improve both the durability and the energy efficiency of the new space. The project timeline was meticulously managed, with weekly updates provided to the homeowners, keeping them informed and engaged. Our team worked diligently to complete the project, overcoming unexpected challenges like minor weather delays, without impacting the overall timeline.
Scope of Work
- Demolition and removal of existing wall sections
- Foundation laying and structural framing
- Electrical and plumbing integration
- Custom window installations for enhanced natural light
- Drywall and painting to match existing interiors
- Installation of energy-efficient HVAC system
Materials & Features
- Bamboo flooring for sustainable elegance
- Energy-efficient double-glazed windows
- Custom cabinetry with soft-close hinges
- LED recessed lighting throughout
Results
- Increased living space by 600 square feet
- Enhanced property value by approximately $95,000
- Improved home energy efficiency by 30%
- Achieved a harmonious blend with original architecture
Project Highlights
- Completed 2 weeks ahead of schedule
- Zero change orders needed
- Achieved full compliance with Tarzana's building codes
- Received a 5-star review on Yelp
Client Testimonial
"We couldn't be happier with our new space! Oria Builders made the process effortless and the result is stunning. The team truly understood our vision and brought it to life."
— John D., Homeowner in Tarzana
Frequently Asked Questions
How long did this room additions project take?
The room additions project in Tarzana took a total of 10 weeks to complete, from initial demolition to final finishes.
What was the total investment for this project?
The total investment for this project ranged between $85,000 and $120,000, reflecting the premium materials and craftsmanship involved.
Did the homeowner need to move out during construction?
No, the homeowners did not need to move out. The project was planned to minimize disruption, allowing them to stay comfortably in their home.
What permits were required for this project in Tarzana?
The project required several permits, including building, electrical, and plumbing permits, all secured through the Los Angeles Department of Building and Safety.